From Health 201FailSystems

how automated healthcare fails, how you'd know, and what to do at each tier — every claim sourced, reviewed continuously


Incident

Main generator at Gaza's Al-Rantisi children's hospital stops; Health Ministry says vital services halted and a smaller generator cannot cover intensive care

On 25 November 2026 the Ministry of Health in Gaza said the main generator at Al-Rantisi Children's Hospital had stopped suddenly, halting a number of vital medical services and, according to Anadolu's Arabic report, the operating rooms of the neighbouring Eye Hospital. The ministry said repairs were hampered by a complete absence of oils and spare parts.

Sources checked when written 28 November 2026

TierThe sources document vital services halted, but they also document a smaller backup generator still running with load-shedding, so loss of power without working backup is not documented; no tier is assigned. How tiers are assigned.

What happened

On Wednesday 25 November 2026, the Ministry of Health in Gaza said the main generator at Al-Rantisi Children's Hospital had stopped suddenly, halting a number of vital medical services inside the hospital. It did not say which services were affected or what caused the breakdown. According to the ministry statement as reported in Arabic by Anadolu Agency, the failure also stopped the operating rooms and service departments of the neighbouring Eye Hospital, which draws its electricity from the same generator. The ministry said engineering teams were trying to restart the generator in extremely difficult conditions, with a complete absence of the oils and spare parts needed, and it gave no expected restart time. The hospital's director, Dr Ayman al-Zahhar, told the Safa news agency that the hospital was running on a generator with much less capacity than the main one, which could not provide minimum services, especially in intensive care, and that departments were shedding load to keep intensive care running. He warned that intensive care, the nursery and the inpatient wards could stop, and that radiology, the laboratory and the emergency department were also at risk. He said the hospital treats 400 to 450 children a day and that its generators had been run without the maintenance or oil changes they needed. On 21 October 2026 the ministry had warned, as reported by Anadolu, that hospital generators had run for thousands of continuous hours without enough oil or maintenance and had reached 'the final point of mechanical danger'. Anadolu also reported the ministry's September statement that 70% of hospital generators were out of service. Anadolu links the shortages to Israeli restrictions on the entry of fuel, lubricants and spare parts. None of the sources reviewed reports a response from Israeli authorities.[1,2,3,4,5]

Documented harm

none documented; the hospital director warned that the failure puts sick children's lives at risk

What it teaches

  • A backup generator much smaller than the main unit forces load-shedding choices, so facilities should decide in advance which departments it must carry.
  • Lubricating oil, spare parts and maintenance belong in power resilience plans alongside fuel, because generators run without them become a growing hazard.
  • When one generator feeds more than one facility, a single failure stops services in all of them, and contingency plans should cover each one.

Sources

  1. غزة.. تعطل مولد كهربائي يوقف الخدمات الطبية في مستشفيين. Anadolu Agency (Arabic), 25 November 2026. Secondary Journalism · link checked 2026-11-28
  2. Un fallo en el generador principal paraliza servicios médicos esenciales en un hospital infantil de la Franja de Gaza. Anadolu Agency (Spanish), 25 November 2026. Secondary Journalism · link checked 2026-11-28
  3. توقف المولد الرئيس لمستشفى "الرنتيسي".. ومديره يحذر عبر "صفا" من وفاة أطفال مرضى. Safa News Agency, 25 November 2026. Supporting Journalism · link checked 2026-11-25
  4. تعطل المولد الرئيس في مستشفى الرنتيسي بغزة يهدد بتوقف العناية المركزة والحضانة. Al-Hadaf News Portal, 25 November 2026. Supporting Journalism · link checked 2026-11-25
  5. Gaza Health Ministry warns hospital generators may shut down. Anadolu Agency, 22 October 2026. Secondary Journalism · link checked 2026-11-28

Lexington, Massachusetts nursing home evacuated after recurring electrical failure; building de-energised

On the night of 24 October 2026 more than 100 residents were evacuated from a nursing and rehabilitation centre in Lexington, Massachusetts, after electrical problems that had recurred over several days. Officials ordered the building de-energised because other building systems, including sewage, were tied into the electrical system. Residents had returned by mid-November, Boston 25 News reported.

Power interruptions at the SPMS data centre take Portugal's national e-prescribing and electronic health record offline

On 19 October 2026, two successive power interruptions at the data centre run by SPMS, the Ministry of Health's shared-services body, left SNS information systems unavailable for several hours. Doctors could not issue electronic prescriptions or consult electronic records, and pharmacies had limited access to prescriptions.

PathPower → Connectivity & data

Two power outages knock out Kemptville hospital's EHR, internet and cellular service and their backups; ambulances diverted

On 13 October 2026 two power outages knocked out Kemptville District Hospital's cellular service, internet, electronic health record and its downtime and backup systems. The hospital declared a code grey, moved to paper, asked lower-acuity patients to go elsewhere and diverted ambulances.

PathPower → Connectivity & data → Human handoff

Prague Central Military Hospital: power cut and failed backup pause operations

Doctors told Seznam Zprávy that a power cut at Prague's Central Military Hospital, which backup generators did not adequately cover, paused all operations for about 20 minutes and left ventilators running on internal batteries. The hospital said the interruption lasted several minutes and did not affect patients' health.

Manzanillo maternity hospital's backup microsystem and generator fail together during Cuban grid outage

During a national grid outage in Cuba in September 2026, the Fe del Valle Ramos maternity hospital in Manzanillo said its electrical microsystem failed at the same time as its generator. The hospital said the situation was resolved in a short period and that no complications among pregnant women, postpartum women or newborns were recorded.

All incidents · Power

Information only, not advice. FailSystems is an aggregation and synthesis of published sources. It is not consulting, engineering, legal, regulatory or medical advice, and using it creates no professional relationship. Health systems are complex and no approach fits every organisation: anything you adopt is your own decision, at your own risk, and should be checked against the current official sources and by qualified people who know your setting. Full disclaimer.

Dealing with an incident right now? This site is a reference, not an incident-response service. Activate your organisation's emergency operations plan and incident command, and: