Manzanillo maternity hospital's backup microsystem and generator fail together during Cuban grid outage

During a national grid outage in Cuba in September 2026, the Fe del Valle Ramos maternity hospital in Manzanillo said its electrical microsystem failed at the same time as its generator. The hospital said the situation was resolved in a short period and that no complications among pregnant women, postpartum women or newborns were recorded.

Fact-checked 11 November 2026

LimitationThe hospital-specific facts come only from the hospital's own statement, which CiberCuba reports was issued on Facebook and which Golfovisión (TV Manzanillo) forwarded on Telegram. The CBS News report covers the national grid collapse and does not mention this hospital.

TierThe hospital states that during the grid outage its electrical microsystem and its generator failed at the same time, leaving no working backup until the fault was resolved. How tiers are assigned.

What happened

Cuba's power grid collapsed on Friday 18 September 2026, which CBS News described as at least the sixth collapse since January (CiberCuba called it the eighth total disconnection of the national grid in 2026). According to Cuban authorities cited by CBS, a failure reportedly occurred in transmission lines in the western part of the country, and CBS reported that some systems serving hospitals and other emergency facilities were being reactivated. The Fe del Valle Ramos hospital issued a statement, which CiberCuba reports was posted on Facebook and which Golfovisión (TV Manzanillo) forwarded on Telegram. In it the hospital said that after the national electricity system went down it was first protected by an electrical microsystem set up to keep essential services running. At 10:30 a.m. that Sunday the microsystem failed, 'coinciding with a failure in the hospital's generator' (CiberCuba's translation). The hospital said the situation was resolved in a short period, restoring the conditions for normal operation. It said staff kept patients under constant monitoring, that no medical complications among pregnant women, postpartum women or newborns were recorded, and that protocols were maintained in the delivery and neonatology services. The sources do not state how long the hospital was without power. CiberCuba reports that an anonymous Facebook post claimed caesarean sections were interrupted and premature babies were moved to the ultrasound area for lack of electricity; the hospital labelled that post 'FALSE'.[1,2,3]

Documented harm

None documented; the hospital stated that no complications were recorded and labelled reports of interrupted caesarean sections false.

What it teaches

  • Layered backups can fail at the same moment, so plans for delivery and neonatal areas should cover a short period with neither grid nor backup power.
  • Where grid collapses recur, the reliability of on-site generation and its switching, not the speed of grid restoration, decides whether hospitals keep power.

Sources

  1. Hospital Fe del Valle Ramos statement on microsystem and generator failure (IPT, relayed by Golfovisión). Golfovisión TV-Manzanillo, 20 September 2026. Supporting Journalism · link checked 2026-11-02
  2. Manzanillo Maternity Hospital acknowledges blackout following SEN failure: "No medical complications were recorded.". CiberCuba, 20 September 2026. Supporting Journalism · link checked 2026-11-02
  3. Cuba's power grid collapses again, leaving millions without electricity for at least 6th time this year. CBS News, 19 September 2026. Secondary Journalism · link checked 2026-11-02

Power interruptions at the SPMS data centre take Portugal's national e-prescribing and electronic health record offline

On 19 October 2026, two successive power interruptions at the data centre run by SPMS, the Ministry of Health's shared-services body, left SNS information systems unavailable for several hours. Doctors could not issue electronic prescriptions or consult electronic records, and pharmacies had limited access to prescriptions.

PathPower → Connectivity & data

All incidents · Power · Cascades

Information only, not advice. FailSystems is an aggregation and synthesis of published sources. It is not consulting, engineering, legal, regulatory or medical advice, and using it creates no professional relationship. Health systems are complex and no approach fits every organisation: anything you adopt is your own decision, at your own risk, and should be checked against the current official sources and by qualified people who know your setting. Full disclaimer.

Dealing with an incident right now? This site is a reference, not an incident-response service. Activate your organisation's emergency operations plan and incident command, and: