From Health 201FailSystems

how automated healthcare fails, how you'd know, and what to do at each tier — every claim sourced, reviewed continuously


Incident

Northeast blackout: New York City hospital generators fail

During the 2003 blackout multiple NYC hospital emergency generators failed. The outage was associated with about 90 excess deaths citywide.

Fact-checked 18 November 2026

TierThe NYC health department lists failures of multiple hospital emergency generators. How tiers are assigned.

What happened

The NYC health department's account lists failure of multiple hospital emergency generators, risk to patients dependent on powered equipment, and loss of ED data feeds to syndromic surveillance among the blackout's public health effects. A later time-series study estimated about 90 excess deaths in New York City, with accidental deaths up 122% and disease-related deaths up 25%.[1,2]

Documented harm

About 90 excess deaths citywide (Anderson & Bell 2012); deaths inside hospitals attributable to generator failures not documented in the sources reviewed.

What it teaches

  • Generators that pass routine tests can still fail on a real, sustained demand.
  • Surveillance data feeds are part of the power-dependent stack.

Sources

  1. Blackout of 2003: public health effects and emergency response. Public Health Reports, 2006. Primary Peer-reviewed · link checked 2026-11-02
  2. Lights out: impact of the August 2003 power outage on mortality in New York, NY. Epidemiology, 2012. Primary Peer-reviewed · link checked 2026-11-02

Power interruptions at the SPMS data centre take Portugal's national e-prescribing and electronic health record offline

On 19 October 2026, two successive power interruptions at the data centre run by SPMS, the Ministry of Health's shared-services body, left SNS information systems unavailable for several hours. Doctors could not issue electronic prescriptions or consult electronic records, and pharmacies had limited access to prescriptions.

PathPower → Connectivity & data

Manzanillo maternity hospital's backup microsystem and generator fail together during Cuban grid outage

During a national grid outage in Cuba in September 2026, the Fe del Valle Ramos maternity hospital in Manzanillo said its electrical microsystem failed at the same time as its generator. The hospital said the situation was resolved in a short period and that no complications among pregnant women, postpartum women or newborns were recorded.

All incidents · Power · Cascades

Information only, not advice. FailSystems is an aggregation and synthesis of published sources. It is not consulting, engineering, legal, regulatory or medical advice, and using it creates no professional relationship. Health systems are complex and no approach fits every organisation: anything you adopt is your own decision, at your own risk, and should be checked against the current official sources and by qualified people who know your setting. Full disclaimer.

Dealing with an incident right now? This site is a reference, not an incident-response service. Activate your organisation's emergency operations plan and incident command, and: